Construction of New and Rehabilitation of Berkads

Clients

KFW through Ministry Of Agricultural Development

Services

Construction

Location

Gabiley

Project Overview

In ongoing efforts to enhance water infrastructure, this project involved both the construction of new berkeds and the rehabilitation of existing, degraded berkeds. The dual approach aimed to maximize water retention capacity and extend the lifespan of traditional water harvesting facilities.

New berkeds were constructed using precision excavation and layered foundation techniques to ensure structural stability. Rehabilitation works included cleaning, structural repairs, re-masonry, and sealing to restore water-tightness and improve durability.

Our project team consisted of three civil engineers and 28 skilled workers, including masons and equipment operators. The work was supported by a fleet of heavy machinery, enabling efficient earthworks and material handling.

Technologies Used:

Barkeds excavation - KEEPS Sanitation and Construction

Precision excavation

Structural rehabilitation and sealing - KEEPS Sanitation and Construction

Structural rehabilitation and sealing

Layered compaction and foundation reinforcement - KEEPS Sanitation and Construction

Layered compaction and foundation reinforcement

Masonry restoration 2 - KEEPS Sanitation and Construction

Masonry restoration

Equipment Deployed:

Project Impact

Through this project, water storage capacity in the targeted areas was significantly increased, reducing water scarcity impacts. The rehabilitation of berkeds extended their usability, preserving essential community water resources with a cost-effective and sustainable solution.